COVID-19: Pipeline Project Status Treatment & Guidance
Scenario: Project has no confirmed open date with bookable/rentable rooms and construction has halted.
Treatment: Deferred status, open date removed
Scenario: Project has confirmed bookable/rentable rooms with an open date that has been extended by 1+ month due to COVID-19.
Treatment: In Construction status, extension to confirmed open date
Scenario: Project had a confirmed bookable/rentable rooms open date which is no longer available, with no further open date available, or has extended 3+ months.
Treatment: Deferred status, no change to open date
Scenario: Project has a confirmed open date which is being extended by a week with no confirmation due to COVID-19.
Treatment: In Construction status, open date extended
Scenario: Project has been marked on hold, and information has not been confirmed as COVID-19 related.
Treatment: Deferred status, open date removed (standard STR treatment)
Scenario: A project’s expected completion date has been extended by 1+ month/s:
Treatment: Not marked as deferred, open date extended (standard STR treatment)
For additional questions or support, please contact pipeline@str.com.